| Project
Name |
Bellevue/92/TFR Intersection - Intersection Improvements |
| Location |
Daytona
Beach |
| Contractor |
P&S Paving, Inc. |
| Project
# |
5232 |
| Begin
Date |
|
| End
Date |
|
| Project
Cost |
$
1.1M |
| Status |
100%
Complete |
| Project
Name |
Clyde Morris Blvd (LPGA to Aberdeen) - 2LN to 4LN |
| Location |
Daytona
Beach |
| Contractor |
Halifax
Paving |
| Project
# |
4833-1 |
| Begin
Date |
12/01/06 |
| End
Date |
02/24/08 |
| Project
Cost |
$
6,877,172 |
| Status |
75%
Complete |
| Project
Name |
Clyde Morris Blvd (Aberdeen to Falls Way) - 2LN to 4LN |
| Location |
Ormond
Beach |
| Contractor |
Halifax
Paving |
| Project
# |
4833-2 |
| Begin
Date |
10/4/07 |
| End Date |
|
| Project
Cost |
|
| Status |
|
| Project
Name |
DeBary Av
Clearing and Grubbing (Deltona Blvd to Providence
Blvd) |
| Location |
Enterprise, Deltona |
| Contractor |
4 Jays
Management, Inc. |
| Project
# |
4351 |
| Begin
Date |
6/14/07 |
| End
Date |
9/12/07 |
| Project
Cost |
$
.136M |
| Status |
100%
Complete |
| Project
Name |
DeBary Av
Bypass (Deltona Blvd to Providence Blvd) - New 4LN |
| Location |
Enterprise, Deltona |
| Contractor |
Halifax
Paving |
| Project
# |
4351 |
| Begin
Date |
|
| End
Date |
|
| Project
Cost |
$7.5M |
| Status |
|
| Project
Name |
Howland Blvd
(Elkcam to Courtland) - 2LN to 4LN |
| Location |
Deltona |
| Contractor |
P&S
Paving, Inc. |
| Project
# |
4836 |
| Begin
Date |
04/27/07 |
| End
Date |
10/13/09 |
| Project
Cost |
$13.3M |
| Status |
63%
Complete |
| Project
Name |
Rhode Island
Av West Extension (US 17 to Westside Pkwy) - New 2LN |
| Location |
Orange City |
| Contractor |
Built Rite
Construction, Inc. |
| Project
# |
4911 |
| Begin
Date |
01/07/08 |
| End
Date |
01/31/09 |
| Project
Cost |
$10.2M |
| Status |
35%
Complete |
| Project
Name |
Tenth Street
(Tatum to Myrtle) and Utility Construction - 2LN to 4LN |
| Location |
New
Smyrna Beach |
| Contractor |
Built Rite
Construction, Inc. |
| Project
# |
4906 |
| Begin
Date |
10/17/2005 |
| End
Date |
1/29/08 |
| Project
Cost |
$
4.8M |
| Status |
100%
Complete |
| Project
Name |
Williamson Blvd (US 92 to Dunn) - 2LN to 4LN |
| Location |
Daytona
Beach |
| Contractor |
Halifax
Paving, Inc. |
| Project
# |
4739 |
| Begin
Date |
06/10/2006 |
| End
Date |
12/12/2008 |
| Project
Cost |
$
6.3M |
| Status |
99%
Complete |
| Project
Name |
S. Williamson Blvd (Spruce Creek to N. of Taylor
Rd) - 2LN to 4LN |
| Location |
Port
Orange |
| Contractor |
Masci
Corporation |
| Project
# |
4740-1 |
| Begin
Date |
6/18/07 |
| End
Date |
6/07/09 |
| Project
Cost |
|
| Status |
30%
Complete |